Katthankudy - Status as of 6th October 2006

At present, 30 houses have been completed and handed over to the Recipients. Please find their List of Names and some photographs taken on site attached for your information and perusal.
The remaining 20 houses of the First Phase of 52 houses have been temporarily suspended on account of the political situation and also due that area being inactive on account of "Idh" fasting, as this area is essentially a Muslim populated area.

We hope to resume work soon after fasting is over by about the 1st week of November, with the same contractor as before (ie. Building and Engineering). However, he will be provided with labour staff from the area, supplied by the Federation Housing Committee of Kathankudy.

We will keep you posted on future goings on, as and when it occurs.