Monday, March 27, 2006

Kalutara Housing Project - Update REPORT

The below link is a Updated Status Report on the Kalutara Housing Project as of 23rd February 2006.

http://www.rotarycregency.org/kalutara_proposal_update_23feb2006.pdf

Saturday, March 25, 2006

Kalutara Housing Project - Project Underway


Close up of foundations structure. Pictures taken on 25th Feb 2006

Kalutara Housing Project - Project Underway


More foundations being completed. Pictures taken on 25th Feb 2006

Kalutara Housing Project - Project Underway


Land cleared and foundation laying started. Pictures taken on 25th Feb 2006

Monday, March 06, 2006

Almost Complete!


President Shantha and Rtn. Ross soon after inspecting a nearly complete house in Katthankudy, Batticaloa during the site visit in February.

The Housing Comittee


Members of the Housing Comittee during the site visit in February.

(Rear L-R) Bary, Shantha, Altaf, Nilesh
(Front L-R) Thorsten, Bilal, Prabhu, Dedunie, Ross

Signing of the Trust


Rtn. Prabhu - Housing Comittee Chairperson (Left) signing the Trust with the Housing Federation Members while Rtn. Bary - Treasurer and Incoming President looks on.

Workforce Mobilised


Workmen at site, carrying out work on schedule.

Under Construction


A section of a house nearing completion.

The Brick Machine


Workmen moulding cement bricks on site at Katthankudy, Batticaloa.

Workforce Mobilised


Another Foundation being completed by the dedicated workforce in Batticaloa.

Site Visit - February 2006


Section of the houses nearing completion.